Trade Finance · Approx. 10 min
Checking an SBLC the Day It Arrives: A Worked Example
A fictional standby arrives by email two days before shipment. Ten checks, one timeline and one amendment request decide whether it is security at all.
Start with the worked example and downloadable worksheet
Questions this guide addresses
- What should a beneficiary check before relying on a standby it has just received?
- How much time does the drawing window really leave once courier and refusal periods are counted?
- Which terms should be amended before goods are shipped?
PentaBay working example
Receipt worksheet: ten checks on a fictional standby
Turn the day-of-receipt checks into a decision before goods are shipped.
Fictional teaching example, not legal or financial advice, not reviewed by legal counsel. Invented standby and sale: USD 520,000 invoice, USD 450,000 standby subject to ISP98, expiry 90 days after issue, shipment day 30, payment due day 60. ISP98 rule numbers checked in the ICC Digital Library on 16 November 2026. Source page: https://pentabay.org/en/insights/sblc-receipt-check-worked-example
Each row records what the instrument says, what was checked, who checked it, when and on what evidence, and one status: OK, Ask (needs an answer or amendment before shipment) or Reject as drafted.
OK means only that the named check was done; it is not credit or legal approval. Any "Reject as drafted" row means the standby cannot be relied on in its current form, whatever the other rows say.
| # | Check | Finding in the example | Status | Action | Checked by, date, evidence (fill in) |
|---|---|---|---|---|---|
| 1 | How did it arrive? | PDF by email from the buyer's agent | Ask | Ask for it to be advised through our bank (a control, not a condition of validity) | |
| 2 | Advised or confirmed by a bank? | Neither | Ask | Decide whether to request confirmation | |
| 3 | Issuer licence and status | Home regulator's register checked; licence seen, no restriction listed | OK | Re-check before shipment and before any demand; not a credit check | |
| 4 | Rules incorporated | ISP98 | OK | Keep the rules text on file | |
| 5 | Expiry and drawing window | Day 90; little room for a corrected demand | Ask | Ask for a longer expiry (example: 60 days after payment due, a negotiating assumption) | |
| 6 | Place and medium of presentation | Paper at the issuer's office abroad | Ask | Allow presentation via our bank or authenticated message | |
| 7 | Documents the beneficiary can produce alone | Applicant-signed certificate required | Reject as drafted | Delete the certificate (ISP98 rule 4.10) | |
| 8 | Amount versus exposure | USD 450,000 of USD 520,000 (86.5%) | Ask | Increase, or agree how the USD 70,000 gap is paid or secured | |
| 9 | Partial drawings | Silent; permitted by rule 3.08 | OK | No change needed | |
| 10 | Transfer and similar wording | "Divisible, assignable and transferable" | Ask | No transfer needed here: may ask to remove (choice). "Divisible" is disregarded (rule 1.10(c)); transfer needs the issuer (incl. any confirmer) or a nominated person to agree and effect it, none nominated here (rule 6.02) |
Apply it to your review
- Fill the worksheet on the day the instrument arrives.
- Record who confirmed each fact, when and on what evidence.
- Send all amendments in one request before shipment.
- Limits: fictional example; general information only; not reviewed by legal counsel. Full explanation and sources: https://pentabay.org/en/insights/sblc-receipt-check-worked-example
Opens in a spreadsheet; contains the example values, not a completed transaction record. Example added: 16 November 2026
Method and verification scope
- The standby, parties, amounts and dates are fictional and were written for this guide. They are not drawn from any real instrument or transaction.
- Rule numbers were checked against the ISP98 text in the ICC Digital Library on 16 November 2026. Courier and preparation times are assumptions; replace them with your own.
- This is general practice information, not legal or financial advice, and it has not been reviewed by legal counsel. Outcomes depend on the instrument's wording and the governing law.
01 · The instrument
A fictional standby arrives two days before shipment
Everything in this example is invented for teaching. No real bank, buyer, instrument or amount is referred to. A Korean exporter has agreed to ship goods worth USD 520,000 on 30-day payment terms. The buyer promised a standby letter of credit as payment security. Two days before loading, the buyer's agent emails a PDF headed "MT760 copy".
The exporter's finance lead reads it with the ten checks in the worksheet below. The terms that matter are summarised in the table.
| Term | What the PDF says |
|---|---|
| Issuer | An offshore-licensed bank (fictional) |
| How it arrived | PDF by email from the buyer's agent; no bank has advised it |
| Amount | USD 450,000 |
| Rules | Subject to ISP98 |
| Expiry | 90 days after issue, at the issuer's counters |
| Place and medium of presentation | Paper documents at the issuer's office abroad |
| Documents required | Beneficiary's signed demand; copy of the unpaid invoice; a certificate signed by the applicant confirming non-payment |
| Other wording | "Divisible, assignable and transferable" |
Fictional teaching example. Amounts and periods are assumptions.
02 · Route and issuer
Who has actually checked this message, and who is bound by it
Under ISP98 rule 2.05, unless an advice states otherwise, it signifies that the advisor has checked the apparent authenticity of the message it received. Here no advisor exists: the exporter holds an email attachment whose sender is the buyer's side. A standby does not need to arrive by bank message to be valid, but routing it through the exporter's own bank is a control worth asking for: a bank then checks its apparent authenticity. Banks exchange undertakings as MT 760 messages; a picture of one proves nothing about its route.
No bank has confirmed the standby either. ISP98 rule 1.09 defines a confirmer as a person that adds its own undertaking at the issuer's nomination. Without one, payment depends on the offshore issuer. Find its home regulator and check, on the day and with the date noted, its licence and any conditions or restrictions on its activities. Public registers such as the UK FCA register or the MAS Investor Alert List are examples, relevant only to institutions those regulators cover. A listing on an alert list is not by itself a finding of wrongdoing, and a clean register entry is neither a credit assessment nor legal clearance.
03 · The drawing window
Ninety days of validity leave little room for a corrected demand
The standby expires 90 days after issue. Shipment is planned for day 30 and the buyer pays 30 days later, on day 60. Presentation must be on paper at the issuer's office abroad (ISP98 rules 3.04 and 3.06). With no time of day stated, expiry is at close of business at the place of presentation (rule 9.04). A presentation is timely if it is made before expiry (rule 3.05); the issuer's examination and payment can fall after that.
The table uses one illustrative calendar: day 0 is a Tuesday, business days are Monday to Friday with no public holidays at either place, the contract due date falls on Saturday day 60 with no rollover, each dispatch goes out on the next business day, courier delivery takes 7 calendar days, a refusal notice arrives the day it is sent, and the correction takes one full business day after the notice day. Rule 5.01 counts from the business day after presentation; a notice within three business days is not unreasonable, one after seven business days is unreasonable, and anything in between depends on the circumstances. Seven business days can be 9 or more calendar days. Holidays, slower couriers or a later shipment all shorten the window.
The cure timeline only works for a clerical discrepancy the exporter can fix alone in one business day. It assumes the applicant-certificate requirement in the next section has already been removed by amendment: as received, that requirement cannot be cured by the exporter at all.
| Step | Notice on business day 3 | Notice on business day 7 |
|---|---|---|
| Payment due, unpaid | Day 60 (Sat) | Day 60 (Sat) |
| First demand dispatched | Day 62 (Mon) | Day 62 (Mon) |
| Received by issuer (7 days courier) | Day 69 (Mon) | Day 69 (Mon) |
| Refusal notice received | Day 72 (Thu) | Day 78 (Wed) |
| Clerical fix done (one business day) | Day 73 (Fri) | Day 79 (Thu) |
| Corrected demand dispatched (next business day) | Day 76 (Mon) | Day 80 (Fri) |
| Corrected demand received | Day 83 (Mon) | Day 87 (Fri) |
| Days left before expiry (day 90, Mon) | 7 | 3 |
Illustrative only. A further refusal of the corrected demand would leave no realistic time to present again before expiry.
Sources [1]
04 · Documents and wording
One required document is in the buyer's hands, and the cover is short
The applicant's certificate of non-payment is the decisive defect. ISP98 rule 4.10 says a standby should not require a document issued, signed or counter-signed by the applicant, and that if it does, the issuer cannot waive the requirement and is not responsible if the applicant withholds it. A buyer that does not pay is unlikely to sign a certificate saying so. As drafted, the exporter may never be able to make a complying demand.
The amount covers USD 450,000 of a USD 520,000 invoice: 86.5%, leaving USD 70,000 unsecured. Partial drawings need no extra wording, because rule 3.08 permits them unless the standby says otherwise.
The phrase "divisible, assignable and transferable" mixes terms with different effects. Under rule 1.10(c), "divisible" has no single accepted meaning and is disregarded, and "assignable" is disregarded unless the context gives it a meaning. "Transferable" does have one: under rule 6.02, a standby that says only that it is transferable lets the drawing rights be transferred in full, more than once, and only if the issuer (including any confirmer) or a person specifically nominated in the standby agrees to and effects the transfer. This example nominates no one. Assigning the proceeds is a separate matter (rule 6.06). The ICC Financial Investigation Bureau lists the same phrase among wording seen in fake guarantees; that alone proves neither fraud nor invalidity. In this direct sale the exporter has no need to transfer, so it can choose to ask for the wording to be removed and keep the instrument plain.
05 · Decision
Do not ship against it as received; send one amendment request
The worksheet ends with six "ask" items and one "reject as drafted". The exporter holds the goods and sends the buyer a single amendment request, listed below, with a date for the reply. Shipping first would give away the leverage that makes amendments happen.
Outcome A: the standby comes back amended, is advised through the exporter's bank, and the USD 70,000 gap is prepaid or otherwise secured. The exporter can ship. Risks remain: the offshore issuer's ability and willingness to pay, the exporter's own documentary and timing compliance, and enforcement against an offshore issuer if it dishonours. A confirmation would reduce the first.
Outcome B: the buyer will not amend or will not let a bank verify the instrument. The exporter then treats the standby as unusable for this sale, which is a commercial decision, not a finding that it is legally invalid. Prepaying only the USD 70,000 gap would leave USD 450,000 exposed, so the exporter asks for full prepayment or other acceptable security for the whole USD 520,000, such as a confirmed letter of credit, or does not ship.
- Have the standby advised through our bank by authenticated message (a control we ask for, not a condition of validity).
- Delete the applicant-signed certificate from the required documents.
- Allow presentation through our bank or by authenticated message, not paper at the issuer's office only.
- Extend expiry. In this example we ask for 60 days after the contract payment date; that is a negotiating assumption that leaves room for a corrected demand, not an ISP98 minimum. Recalculate if shipment or the payment date moves.
- Increase the amount to USD 520,000, or agree in writing how the USD 70,000 gap is paid or secured.
- Remove "divisible, assignable and transferable", since no transfer is needed in this sale (a commercial choice).
Practical takeaways
- A PDF in an email is not an advised standby; ask for it through your bank so its apparent authenticity is checked.
- A document the applicant must sign can block every demand; ISP98 rule 4.10 says the issuer cannot waive it.
- Count the drawing window from the contract payment date, not from issue, with your own calendar, courier and holiday assumptions.
- Decide before shipment: amend and verify, or treat the standby as unusable and secure the whole exposure another way.
Sources and further reading
Source titles are preserved in their original language. Figures retain the reference period stated by each source.
- International Chamber of Commerce (ICC Digital Library) International Standby Practices (ISP98), rules text ↗ (opens in a new tab)
Rules 1.06, 1.09 (confirmer), 1.10(c), 2.05, 3.04, 3.05, 3.06, 3.08, 4.10, 5.01, 6.02, 6.06 and 9.04 checked against this text.
Accessed 2026-11-16 - Trade Finance Global How do banks talk to each other and what are the different types of messages used by SWIFT? ↗ (opens in a new tab)
Describes MT 760 as the message carrying an undertaking between banks. Confirm current formats with your bank.
Accessed 2026-11-16 - International Chamber of Commerce FIB warns of fake bank guarantees ↗ (opens in a new tab)
ICC Financial Investigation Bureau notice listing warning wording, including "divisible, assignable and transferable".
Accessed 2026-11-16 - Monetary Authority of Singapore Investor Alert List ↗ (opens in a new tab)
Example of a regulator alert list; MAS states it is not exhaustive and points to its Financial Institutions Directory for licensed entities.
Accessed 2026-11-16 - UK Financial Conduct Authority Financial Services Register ↗ (opens in a new tab)
Example of a public register for checking an institution's authorisation status on a given date.
Accessed 2026-11-16