Bitumen Procurement · Approx. 12 min
Bitumen Landed Cost: A Worked Example from CFR Price to Delivered Cost per Tonne
The cheapest quotation per tonne is not always the cheapest bitumen at your site. Build the cost line by line, divide by the net tonnes you can actually use, and test what moves the answer.
Questions this guide addresses
- Which cost lines turn an FOB or CFR price into a delivered cost per tonne?
- Why should the total be divided by net bitumen tonnes rather than gross or drum count?
- How much do freight, price, exchange rate and drum fill move the result?
- How do you compare an FOB quote with a CFR or CIF quote on equal terms?
- How does the June 2012 result compare with public price indications for the second half of 2026?
Method and verification scope
- Price basis: June 2012. The CFR price, quantity, container count and drum specification come from a June 2012 drummed shipment handled by an earlier trading company associated with PentaBay's management, rounded. Bitumen prices then differ greatly from today, so the figures show the method, not a current price.
- That shipment's documents do not show insurance, destination charges, inspection, duty or inland transport, because the buyer arranged them separately. Those lines are illustrative assumptions prepared in October 2026, not market quotes. No counterparty, port, country, document number or exact date from the shipment is disclosed.
- The arithmetic follows the PentaBay bitumen landed-cost calculator on this site. Tariff classification and duty rates vary by destination and change over time; confirm them with the destination customs authority or a licensed customs broker. This is general information, not tax or customs advice.
- Second-half 2026 comparison: drummed 60/70 price indications for July and August 2026 were taken from two weekly industry market reports, listed in the sources and checked on 29 October 2026. They are indicative ranges, not transaction prices or PentaBay quotations, and freight and insurance for 2026 were not verified.
01 · Why it matters
A quotation price is where the cost calculation starts
Bitumen quotations arrive in different shapes. One supplier quotes FOB per metric tonne at the loading port. Another quotes CFR to your port. A third quotes per drum, and a fourth includes the drums in a per-tonne price without saying whether the tonne is net or gross. Placing these figures side by side compares delivery terms and weight bases, not bitumen costs.
The method in this guide puts every quotation on the same basis: the cost of one net tonne of bitumen that reaches your site and can be used. It needs four inputs. They are the quotation basis under Incoterms®, the net quantity, every cost the quotation does not include, and realistic assumptions about fill and loss.
02 · The example
Ten containers of 80/100 in drums
The example follows a June 2012 shipment of penetration grade 80/100 bitumen in new steel drums. The order was about 200 net tonnes in ten 20-foot containers. Each container held 110 drums, 1,100 drums in total. The proforma invoice stated a net weight of 180 kg per drum, plus or minus 3 kg, and a gross weight of 190 kg per drum, plus or minus 3 kg. Drum tare is part of the shipped weight but not part of the bitumen the buyer pays for per net tonne.
The supplier quoted USD 575 per net tonne CFR the destination port, drums included. On 200 tonnes that is USD 115,000. Freight was in the price, and the contract left insurance to the buyer. The buyer therefore adds insurance and every destination cost up to the site. If your quotation is FOB, add ocean freight before insurance, as the comparison section explains.
Quotation basis
CFR [destination port], drums included. Insurance for the buyer's account.
Quantity
10 containers × 110 drums, stated at 180 kg net per drum; invoiced on 200 net tonnes.
Price
USD 575 per net tonne (June 2012 shipment, rounded), so the goods cost USD 115,000.
03 · Step by step
Build the cost from the loading port to the site
Work in the order the cargo moves. Keep a note of whether each line is charged per container, per bill of lading or per shipment. The price is from the June 2012 shipment. Every other line below is an illustrative assumption, because the buyer arranged those costs outside the supplier's documents.
| Cost line | Basis | Calculation | USD |
|---|---|---|---|
| Goods (CFR, freight included) | Per net tonne, June 2012 | 200 × 575 | 115,000 |
| Cargo insurance | Assumption | 110% × 115,000 × 0.15% | 190 |
| Destination port and clearance | Assumption, per container and per shipment | 10 × 350 + 300 | 3,800 |
| Discharge-port inspection | Assumption | Per shipment | 800 |
| Import duty | Assumption, % of CIF value | 4% × 115,190 | 4,608 |
| Inland trucking | Assumption, per container | 10 × 450 | 4,500 |
| Landed cost | Total | Sum | 128,898 |
| Landed cost per net tonne | Total ÷ 200 | 128,898 ÷ 200 | 644.49 |
Price basis: June 2012 shipment, rounded; prices then differ greatly from today. Other lines are illustrative assumptions prepared in October 2026, not market quotes.
- Goods: 200 net tonnes × USD 575 CFR = USD 115,000. Ocean freight to the destination port is included in this price.
- Cargo insurance (assumption): insured value of 110% of the CFR value (USD 126,500) at an assumed rate of 0.15% gives about USD 190. The CIF value is USD 115,190. Specify Institute Cargo Clauses (A) or (C) when you ask for the premium.
- Destination port and clearance charges (assumption): USD 350 per container for terminal handling, delivery order and handling (USD 3,500), plus USD 300 per shipment for documentation and customs brokerage. Total USD 3,800.
- Discharge-port inspection at the buyer's cost (assumption): USD 800 for sampling and testing against the contract specification.
- Import duty (assumption): 4% of the CIF value, which gives USD 4,608. Look up the actual rate for your HS code (the 2012 documents classified the cargo under subheading 2713.20) and the valuation basis your customs authority applies. Recoverable VAT or GST is left out here because a registered importer normally reclaims it, but it still affects cash flow.
- Inland trucking from port to site (assumption): USD 450 per container × 10 = USD 4,500.
- Total: USD 115,190 + 3,800 + 800 + 4,608 + 4,500 = USD 128,898, or USD 644.49 per net tonne.
04 · Divide correctly
Divide by the bitumen you can use, not by what was shipped
The USD 644.49 figure assumes the cargo holds exactly the 200 net tonnes invoiced and every kilogram reaches the mixing plant. The drum marking allowed 3 kg either way. If the drums had averaged 177 kg, the cargo would hold 194.7 net tonnes, and the same USD 128,898 would cost about USD 662.03 per usable tonne.
In this shipment the packing list showed about 201.0 net tonnes across the 1,100 drums, an average of roughly 183 kg per drum. Divided by 201.0 tonnes, the cost would be about USD 641.28 per tonne. The difference shows why the invoiced quantity, the packing list and the weighing evidence must be reconciled before the cost per tonne is final.
Drummed bitumen also loses some product in handling, because bitumen sticks to the drum wall when the drums are heated and emptied. An assumed 1% handling loss on 200 tonnes leaves 198 usable tonnes and raises the cost to about USD 651.00 per tonne. Your own decanting records are a better guide than any general figure. The drum weight and COA guides on this site cover the related checks.
05 · Packing
Drums and bulk carry different hidden costs
In a drummed quotation the drum itself is part of the price. The buyer pays for steel it will scrap or sell, accepts some decanting loss, and needs heating equipment to empty the drums at the plant. In return, drums move in ordinary containers, can be stored in a yard and can be delivered in small lots to inland sites.
Bulk bitumen removes the drum cost and most of the decanting loss. It needs a heated tanker, a heated receiving terminal and storage, and the parcel size is usually much larger. Compare the two on the same per-usable-tonne basis. Remember that bulk terminal fees, heating energy and minimum parcel sizes replace the drum and container costs rather than removing them.
06 · Sensitivity
Test which inputs move the answer
Change one input at a time and recalculate. In this example the quoted price matters most, because it also raises the insurance and duty, which are charged on value. Local charges paid in local currency matter less. A drum fill shortfall within the marked tolerance moves the result by about as much as a 3% price change.
| Change | New landed cost | Per net tonne | Change per tonne |
|---|---|---|---|
| Quoted price +10% (USD 632.50) | USD 140,877 | USD 704.38 | +59.89 |
| Average drum fill 177 kg (194.7 t) | USD 128,898 for 194.7 t | USD 662.03 | +17.54 |
| Handling loss 1% (198 t usable) | USD 128,898 for 198 t | USD 651.00 | +6.51 |
| Local charges +10% (exchange rate) | USD 129,808 | USD 649.04 | +4.55 |
| Packing list net 201.0 t instead of 200 t | USD 128,898 for 201.0 t | USD 641.28 | −3.21 |
Price: June 2012 shipment, rounded. Other inputs are illustrative assumptions. Duty and insurance are recalculated where the value changes.
07 · Then and now
June 2012 compared with the second half of 2026
The June 2012 price is useful for the method but not for today's budget. To show the gap, the table below sets the 2012 shipment beside public market indications for July and August 2026 and runs the same landed-cost calculation on both. The 2026 range comes from weekly industry reports that quote drummed 60/70 at about USD 600 to 640 per tonne CFR into East and Southeast Asian ports. Those are indicative levels, not prices for any specific trade, and the grade differs from the 80/100 shipped in 2012.
Keeping every other line at the same assumptions, the 2026 range gives a landed cost of about USD 670.53 to 712.20 per net tonne, against USD 644.49 for the June 2012 shipment. Freight and insurance were reported as higher in 2026 because of shipping risk on some routes, so the real 2026 gap is probably wider than the table shows. Price the actual lane, grade and packing before you budget.
| Item | June 2012 shipment | H2 2026 public indications |
|---|---|---|
| Grade and packing | 80/100, new steel drums | 60/70, drums |
| Basis | CFR, freight included | CFR East and Southeast Asian ports |
| Price per net tonne | USD 575 | About USD 600–640 (midpoint USD 620) |
| Goods for 200 t | USD 115,000 | USD 120,000–128,000 |
| Insurance, port, inspection, duty, trucking | USD 13,898 (assumptions) | USD 14,106–14,439 (same assumptions) |
| Landed cost per net tonne | USD 644.49 | USD 670.53–712.20 (midpoint USD 691.37) |
2012: shipment values, rounded; prices then differ greatly from today. 2026: indicative public ranges checked on 29 October 2026 from the sources listed, not transaction prices. Insurance, port charges, inspection, duty and trucking are illustrative assumptions in both columns.
08 · Comparing quotations
Put FOB, CFR and CIF quotations on one line
To compare an FOB quotation with a CFR or CIF quotation, add to each only what it leaves out. For FOB, add freight and insurance. For CFR, add insurance. For CIF, check that the cover is adequate and add any extra cover you need. Destination costs, duty, trucking, fill and loss adjustments then apply to all three in the same way. Check also where the risk passes. A CFR quotation that is cheaper by USD 10 per tonne still leaves the buyer carrying the sea risk from the loading port.
Read the freight scope as well. A CFR price may include ocean freight but exclude destination terminal handling, which the line will bill to the consignee. A quotation per drum must be converted to a net-tonne price with the stated fill before it can be compared.
09 · Try it
Run your own numbers in the calculator
The bitumen landed-cost calculator on this site follows the same arithmetic. Choose the quotation basis, enter the net quantity and the quoted price per net tonne, then enter insurance and other costs for the whole cargo. For this example, choose CFR (freight is then shown as included), and enter 200 tonnes, USD 575, insurance USD 190 and other costs USD 13,708 (port charges, inspection, duty and trucking together). The result is USD 644.49 per net tonne.
The calculator leaves any cost you have not entered as unknown, so an incomplete estimate is never shown as a total. Your inputs stay in your browser. If you want a quotation, you can carry the estimate into the bitumen enquiry form.
10 · Checklist
Before you compare quotations
Ask every supplier and forwarder for the same items, in writing, before you calculate.
- Quotation basis written as rule, named place and edition, such as FOB [port] Incoterms® 2020.
- Price per net tonne, with drums included or excluded, and the net fill per drum and its tolerance.
- Container count and drums per container, or parcel size for bulk.
- Ocean freight with surcharges listed, and whether origin and destination terminal handling are included.
- Insurance clauses, insured value and premium rate, or confirmation that the CIF cover meets your needs.
- Destination charges per container, per bill of lading and per shipment, with currency.
- HS code, duty rate and valuation basis confirmed with customs or a licensed broker.
- Inspection company and cost at loading and discharge, and which result is final.
- Inland transport, container free days and detention, and your own handling loss from past deliveries.
- Validity date of each price and rate, because the calculation is only as current as its oldest input.
Practical takeaways
- Start from the quotation basis: under FOB you add freight and insurance; under CFR you add insurance; under CIF you add neither, but you still check the cover.
- Collect destination costs per container, per bill of lading and per shipment separately, because they scale differently.
- Divide by net bitumen tonnes, then adjust for drum fill and handling loss before comparing suppliers.
- The quoted price moves the answer most; drum fill and loss assumptions can move it as much as a small price discount.
- The price, quantity and packing come from a June 2012 shipment, rounded; prices then differ greatly from today. Other costs are illustrative assumptions. Confirm actual prices in writing at the time of quotation.
Sources and further reading
Source titles are preserved in their original language. Figures retain the reference period stated by each source.
- International Chamber of Commerce Incoterms® 2020 ↗ (opens in a new tab)
Allocation of freight, insurance and risk under FOB, CFR and CIF used to decide which cost lines to add.
Accessed 2026-10-29 - World Customs Organization What is the Harmonized System (HS)? ↗ (opens in a new tab)
Background on HS classification; national tariffs set the duty rate for the relevant subheading.
Accessed 2026-10-29 - International Maritime Organization Verification of the Gross Mass of a Packed Container ↗ (opens in a new tab)
Gross mass of packed containers, which includes drum tare and container tare, as distinct from net product.
Accessed 2026-10-29 - Lloyd's Market Association Joint Cargo Committee: Cargo Clauses ↗ (opens in a new tab)
Institute Cargo Clauses (A) and (C) referred to when requesting an insurance premium.
Accessed 2026-10-29 - Bitumenmag (WPB Journal) Global Bitumen Price, Week 2 of August 2026 ↗ (opens in a new tab)
Weekly indicative levels by grade, packing and basis; drummed 60/70 CFR into East and Southeast Asian ports around USD 600–625 per tonne as of 11 August 2026. Indications, not transaction prices.
Accessed 2026-10-29 - Bitumen Price (bitumenprice.org) Asia-Pacific & Middle East bitumen market report, 28 July 2026 ↗ (opens in a new tab)
Weekly market report; Southeast Asian buying interest around USD 630–640 per tonne CFR and regional FOB levels for July–August 2026 cargoes.
Accessed 2026-10-29